GC updates of SG-PBE section as of today 13th Jan 2024.
1- Track is 100% complete between PBE-MALA and only remaining in Mala range forest.
2-There is a bridge incomplete in Mala Forest where Girder has been launched today and it is expected that track will be laid within this month and Poles foundation will start within this month along with wiring.
...
more...
Section is expected to complete by Feb end, It will provide a new route to NDLS, KGM from LJN.
It is still not clear whether this section will be opened for public before elections.
please wait...Translate to EnglishGC updates for the SG-PBE section as of today, January 13th, 2024:
1- The track is fully done between PBE-MALA, only left to do is work in Mala range forest.
2- There's a bridge that's not finished in Mala Forest, but they launched the girder today. They expect to lay the track and start with the poles foundation and wiring within this month.
They plan to finish the section by the end of February, which will give a new route to NDLS and KGM from LJN.