MLY Bypass to Ghatkesar Quadrapling is already done, it's idle since last 1.5yrs, BMO MED Doubling n Electrification is also completed n commissioned. MJF to MED Electrification was also commissioned last year. Sanathnagar to MLY Bypass doubling works in progress. Falaknuma to Umdanagar Doubling in progress. I guess they're still trying to convince airport authorities for MMTS services till Airport. They're planning to extend phase 2 upto Raigir, for tge convinience of Yadadri Temple pilgrims. Already tripling works started from Raigir End, Raigir Pf is broken n land levelling is being done. So Ghatkesar to Raigir will be Triple line soon.