Updates regarding pfm-prg doubling.
In my last blog post /blog/post/4279560 on 03rd April, the ends on both the sides of pfm-south ganga bridge were having trees, jungles etc but this time on 13th June, both the sides have been almost layer formed with soil and then blast for laying of tracks. If the work continues with same speed in monsoon also, prg-pfm doubling will complete by sep-oct.
Pic 1: ganga bridge south (prg) side soil and blast layer is being covered from side with stones to prevent soil erosion.
Pic...
more... 2, 3& 4: Levelling work view of south side of bridge from different distances.
I also recorded a knowledgeable video at the venue but can't upload as I don't have youtube channel and 463 mb video ( 4 mins) cannot be emailed also (as No email can be send above 15 mb).
So if any member can upload the video on his channel, he is requested to send me his whatsapp no. in a pvt blog to me.