Quarter-wise and Project-wise Target(2019-20 ) for Railway Electrification under Project Office : New Jalpaiguri.
.
Quarter-1 Target for 2019-20
GROUP - RLY SECTION - RKM
150 - NFR Gunjariya-NJP- Raninagar jalpaigudi - 95
....
more...
Quarter-2 Target for 2019-20
GROUP - RLY SECTION - RKM
257 - NFR Guwahati-Lohani - 100
256 - NFR New Bongaigaon-Dudhnoi - 72
.
Quarter-3 Target for 2019-20
GROUP - RLY SECTION - RKM
256 - NFR Dudhnoi – Bamuni Gaon - 50
.
Quarter-4 Target for 2019-20
GROUP - RLY SECTION - RKM
256 - NFR Bamuni Gaon-Kamakhya - 53