Here i present the full doubling update of BZA BVRT
1. Bridge on BUDAMERU which was immediately after bza parllel to BZA VSKP main line
2.bed works done with optical boxes curving out to GDV BVRT NDD LOOP
3. immediately after curve there was need of 2 bridges side by side work was still at starting phase
4,5....
more... Electrification poles with sub raise between ramvarapadu and nidamanuru
6. MTM AJMER SPL rake parked at nidamanuru
7. After nidamanuru till uppaluru doubling plus poles done
8,9. Post uppaluru till GDV and moturu bed works are done sleepers placed a side and small bridges were going on
10. After moturu till AKVD max works completed including bridges station new pfs done but new station building's are pending
11. New pf at MVP station
12,13,14. Mandvalli station with new pf new station boards and interlocking completed with signal posts
15,16. Interlocking and pf works at KKLR
17. Post KKLR
18,20,21. This is the largest bridge of entire section track is also layed poles are pending here only on the bridge
22. Interlocking works going on at AKVD
23. Bed works done post AKVD but sleepers are placed and some places arranged for put the rails
24. some part before UNDI track was done
25. UNDI canal steel bridge same as old one