The line would originate from dhn only......from kusnda to bhuli a double line will be laid.....from bhuli to nichitpur the line would run parallle to the Grand chord....from nichitpur till tundu the new line will be built....from tundu it will merge with the existing DC line.....the work will begin on nichitpur-tundu section first.....work will begin as soon as dgms gives it clearance....by work I mean land acquisition.....the telo bypass is a budget related proposal, can't say much about it..... don't have much info on Dhn sonnagar tripling.....edfc work is in progress but slow....land acquisition has been done for 90% of the areas in Dhn n surrounding region but the West Bengal state govt is not cooperating much for land acquisition till dankuni.....2 lines for GC,2 lines for edfc,2 line for DC line is what I expect as per info what I have