Plz post status of the following GC projects of IR:-
1. UDZ-HMT-ADI. AFAIK ADI-HMT Work going on.
2. JBP-NIR-BTC. AFAIK JBP-NIR Work complete & operational up till Ghunsore. More Plz.
3. IND-KNW-AK. AFAIK IND-DADN(MHOW) is BG now. Sanawad-Khandwa Leg GC going on. More Plz
4....
more... BPR-PBE-SZP/MLN-STP-ASH. Last update ASH-STP work going on full swing. BPR-PBE-TPU leg completed. More Plz.
5. SIKR-RGS-JP. AFAIK Work not yet started. More Plz
6. MVJ-MJ. AFAIK MVJ-NDT is operational BG. NDT-MJ Work not yet started. More Plz.
7. NGP-CWA-NIR-MFR. IAPB Member#1203948. CWA-BDKD - CRS trial successful, no trains yet. BDKD-NGP Work going on. More Plz