SWR #doubling targets for 2018
Tumakuru-Gubbi 18km -- commission in May 2019
Chikjajur-Tolahunse - Harihar 60km
Makalidurga-Devarapalli 36km --- completed
Yelahanka-Doddaballapura 21km
Wandal...
more... - Jumnal-Minchnal 71km
Koppal-Ginigera-Hospet 28km -
#CRS date 16 Nov
Annigeri-Hulkoti-Binkadakatti 18km
Arsikere Kardi 36km - commissiond in last week Nov
#SWR
Mkl dpe completed in March
He (Dhananjay hunasgi)will give you the updates as of now when he will travel on this stretch . Heard 36km between Bhalwani - Wadsinghe stretch will commission in this month as entire track laying works are completed in this section. Only NI works are yet to be done waiting for official announcement by CR for taking block. And about Solapur Kalaburgi section two stretches will commission by next month one is Gulbarga sawalgi second is Boroti Dudhani/ kulali I guess. As these three above stretches which I mentioned above were to be commissioned by last year as per original target set by the railway board . But it crossed these deadlines!!
I know bro . Was informed by friend over what's app. I was the first person to be informed
Sorry for a late reply. I'd been busy for the last 2 months. I'll be travelling to Pune sometime in May-June this year. I'll be covering the stretch again
Tumkuru Gubbi now getting commisssioned.
Makalidurga - Devarapalle double line journey compilation video :)
Thanks for your compliments. Yelahanka - Makalidurga may get completed soon as track laying work is almost over and few bridges are under construction between Oddarahalli and Makalidurga.
The question should be when will DMM-ATP-GY doubling get completed ?? The bottleneck is that section..
Could you please tag it under respective stations.
Bridges between Makalidurga - Oddarahalli were completed long back part of YNK PKD Doubling. The only part pending was MKL major Bridge which got completed recently 5-6 months back during the month of Jan/feb this year 2019 I guess !!