#ElectrificationUpdate #18November2019
DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
Poles - 100%
Brackets - 96% done (Completion expected by 23-Nov-2019)
Wiring - Initiated on 31-Aug-2019 at MBP/Mohibullapur. From DAL/DaliGanj Junction wiring started leaving one...
more... patch for final linking with existing live wire. As per latest update wiring reached till KB station (Just 6Km from STP) moreover OHE van has already started from DAL end and completed till AA/Ataria (Wiring completion expected by 23-Nov-2019 or so).
SSP - 3 SSP's been located at BKT, SD and STP. Two transformer has been placed at BKT SSP and work in progress at STP rest nothing much has progressed (Completion expected by Dec2019 or so)
Block - 4 hours block been requested at DAL and STP respectively on 22-Nov till 24-Nov for connecting with existing live wire. More info awaits.
OHE wire energized - Expected by Dec2019
Trial run : First trial run would be on 29-Nov-2019
CRS inspection - Expected by Dec2019
Commercial uses - Any point of time after successful CRS
** All completion dates are tentative**