Status of #electrification in Gujarat
Grievance Description : Pl provide status n target date of completion of following electrification Ahmedabad Ajmer New Delhi Khodiyar gandhinagar kalol Ahmedabad rajkot Mahesana viramgam samakhiyali Rajkot okha Wankaner maliya miyana Surendranagar dhgndhra Samakhiyali gandhdham kandla Pl section following electrification work Ahmedabad udaipur n nadiad modasa shamlaji with gc work Rajkot somnath Porbandar jetalsar n wansjaliya kanlus Surendranagar pipvav Dhola bhavnagar Mahesana patan bhildi Bhuj adipur Palanpur samakhiyali
Current Status : CASE CLOSED
Date...
more... of Action : 02 Jun 2017
Details : This status of Electrification of the above section is as under:- S.No Section Status
1 Ahmedabad-Ajmer-New Delhi Electrification work is in progress and planned for completion by March,2019.
2 Khodiyar-Gandhinagar-Kalol Statutory Inspection of Commissioner of Railway safety (CRS) was conducted on 31.5.17.
3 Ahmedabad-Rajkot Electrification has been sanctioned at a cost of Rs.320.84 crores and planned for completion by March,2020
4 Mahesana-Viramgam-Samkhiyali Electrification has been sanctioned at a cost of Rs.318.94 crores and planned for completion by March,2020
5 Rajkot-Okha Electrification has been sanctioned at a cost of Rs.333.15 crores and planned for completion by March,2021
6 Wankaner-Maliya miyana Surendranagar-Dharingdhra Electrification has been sanctioned at a cost of Rs.109.11 crores and planned for completion by March,2020
7 Samkhiyali – Gandhidham-Kandla Port Electrification has been sanctioned at a cost of Rs.65.55 crores and planned for completion by March,2020.
8 Ahmedabad-Udaipur Nadiad-Modasa-Shamlaji Electrification of railway tracks is decided on the basis of financial viability, traffic volume and operational feasibility.
At present, there is no proposal to electrify these sections.
9 Rajkot-Somnath, Jatalsar-Porbandar
10 Wansjalia - Kanlus
11 Surendranagar-Pipavav Dhola-Bhavnagar
12 Mahesana-Patan-Bhildi
13 Bhuj-Adipur
14 Palanpur-Samakhiyali Electrificaiton of Palanpur-Bhildi-Samkhiyali will be decided by Board of Director, Kutch Railway.