khurdha road -balangir line can solve problems of coastal corridor of coromondal coast from vskp -vzm-rayagad-balngir-kur-bbs-ctc-hwh trains can be runned ir should complete as soon as possible
----------------->
Khurda – Balangir line: "… the process of separating the government land has been hampered because of the demand of premium for it by the concerned tehsildars. This, when the state government had exempted it.
Between...
more... the 32km and the 112km marks of the line, 1,020 acres are required and out of this, 802 acres have been handed over by the state government.
However, processing of papers for the land acquisition from the 80km to the 112km mark is held up for verification. This patch of land is crucial for the project."