55% work already complete for increasing MPS of Khana - Gumani section in SBG loop ( Khana-NJP main line) from 110 kmph to 130 kmph. Progress of work in last 9 month is very very good.
Tender already floated for Installation of double Distant signal in this section during Feb 2024.
Work...
more... will be completed in this financial year.
please wait...Translate to English55% of the work for boosting the speed from 110 kmph to 130 kmph on the Khana-Gumani section in SBG loop (Khana-NJP main line) is already done. The progress in the last 9 months has been awesome. Tender has been put out for setting up double Distant signal in this area by Feb 2024. Project will be done and dusted this fiscal year.