Expenditure till date- ₹ 833.49 Cr.
🟢Overall Physical Progress - 67%
🔘 Total Length: 132.34 Km
🔘 Length Commissioned - 29.35 Km
🔘 Length remaining - 102.99 km
🔘Land acquisition completed- 125.52/ 136.44 Hectare (70%)
A) Completed Sections: 33.33 km (25.18%)-
Wardha - Hinganghat
B) Near Completion Sections - 47.98 km (36.25%)-
Hingaghat- Chikni Road,
Majri-Tadali
C) In Progress Sections - 51.03 km (38.57%)-
Chikni Road-Majri,
Tadali-Ballarshah
🟢In Progress Works-
☑ Earthwork - 15.16/25.81 Lcum completed (58.73%)
☑ Blanketing- 60000/195000 Cum completed (30.76%)
☑ Important bridges– 1/2 completed. (50%)
☑ Major Bridge– 6 out of 12 in Progress.
☑ Minor Bridge/LHS/RUB- 21/146. (14.68 %)
☑ Station Building- 5/19 (26.30%)
☑ Track linking – 30/ 132 Tkm (22.18%)
☑ Overhead Equipment OHE Foundations -620/2904. (22%)
☑ OHE Mast Erections -368/2640. (14%)
☑ OHE Wiring- 15/132 km (11%)
☑Signalling and Telecommunication works – 3/18 (16%)
🔴Completion of this new 3rd line will reduce congestion on busy Secunderabad- Wardha - Nagpur route and will improve mobility of the trains.