Expenditure till date- ₹ 644.41 Cr
🟢Overall Physical Progress- 50%
🔘Length- 67.35 Km.
🔘Land acquisition completed- 35.96/49.23 Hectare (73%)
🟢In Progress Works-
☑ Earthwork - 9.11/24.04 Lcum.
☑ Blanketing- 2.26 Lcum in progress.
☑ Major Bridge- 5 in progres out of 8
☑ Minor Bridge/LHS/RUB- 23/203 (11%)
☑Station Building- 3/35 in progress
☑ Overhead Equipment OHE Foundations– 200/1400 (15%)
☑ OHE Mast Erections – 170/1200 (14%)
☑Indoor and outdoor signalling works–1 / 12.
🔴Completion of this new 3rd line will reduce congestion of busy Kalyan - Kasara Suburban and mail express route and will improve mobility of the trains.
🔘2990 Crs expenditure done till date.
🔘Progress of doubling/3rd/4th new lines all over Central Railway’s 5 divisions-
🔘CR has completed 161.80 km multitracking (new line/doubling/3rd/4th line) in current FY from April 2023 till date 2023.
🔘3890 Crs planned by CR in this year for new lines/doubling/3rd/4th line.
🔘2990 Crs expenditure done till date
Source:CR X