💰 Cost- ₹ 3445.48 Cr
💰 Expenditure till date- ₹ 1910.07 Cr.
🟢Overall Physical Progress- 47%
🔘Length- 270 Km.
🔘Land acquisition completed- 1911/2138 Hectare (89%)
🟢In Progress Works-
☑Earthwork - 87.54/201.14 Lcum (44%)
☑Formation - 40/284.60 km
☑Major Bridges- 32/80
☑Minor Bridges- 50/320
☑Road over bridge (ROB) - 43 In Progress
☑RUB/LHS– 19/52 in progress
☑Station Building- 3/27
☑Tunnels– 6 in progress of total 8 km length
☑ Track Linking- 28/284.60 track km
🔴Completion of this new line will improve connectivity of Vidarbha and Marathwada region.
🔘Progress of doubling/3rd/4th new lines all over Central Railway’s 5 divisions-
🔘CR has completed 161.80 km multitracking (new line/doubling/3rd/4th line) in current FY from April 2023 till date 2023.
🔘3890 Crs planned by CR in this year for new lines/doubling/3rd/4th line.
🔘2990 Crs expenditure done till date.
please wait...Translate to EnglishYo peeps! Check out this dope update! 💥 We got a new line comin' up from Wardha to Nanded passin' through Yavatmal and Pusad. Nagpur division doin' its thing on this project. 💵 Cost is ₹3445.48 Cr and we've spent ₹1910.07 Cr already. Progress is at 47% and we got 270 Km to cover. Land acquisition 89% complete, we need 1911 out of 2138 Hectares. Still grindin' on that 💪
In the works we got:
✅ Earthwork - 44%
✅ Formation - 40 km outta 284.60 km
✅ Major Bridges - 32 outta 80
✅ Minor Bridges - 50 outta 320
✅ ROB - 43 trucks rollin' in
✅ RUB/LHS - 19 communities outta 52 rollin'
✅ Station Buildings - 3 outta 27
✅ Tunnels - 6 outta 8 km done
✅ Track Linking - 28 outta 284.60 track km
This new line gonna amp up the connection between Vidarbha and Marathwada region, real solid move there. 🚆
Central Railway doin' bits with 161.80 km multitracking in the current year and got a plan of 3890 Crs for new lines. We've spent 2990 Crs already on this hustle. Let's keep hustlin' and making those tracks! 🛤️🔥