Edited Now (Previous update was of 6 June 2023)
Update as of 13 July 2023
Pune Miraj Doubling updates as of
тЧП Pune to Shindawane (32 Km) FEDL
тЧП...
more... Shindawane to Ambale (9 Km)
- Ground Leveling work is in final stage
- Two Viaducts work is completed out of 6 Viaducts
- 3 Viaducts foundation work is completed and pillars are in initial stage
- One Tunnel is in final stage
тЧП Ambale to Nira (43 Km) FEDL
тЧП Nira to Lonand (8 Km)
- Tracks are being laid
- Electrification work on 2nd Line going on
тЧП Lonand to Adarki (17 Km) FEDL
тЧП Adarki to Wathar (10 Km)
- Ground Leveling work is finished (remaining at Wathar outer only)
- New Down PF will come on Loop Line
- Tracks are being laid
тЧП Wathar to Palsi (9 Km)
- Ground Leveling is done in some patches
- Ballast Mountains on some patches..not yet spreaded
тЧП Palsi to Jarandeshwar (9 Km) FEDL
тЧП Jarandeshwar to Satara (8 Km)
- No progess from Jarandeshwar side
- Some work visible from Satara side
тЧП Satara to Koregaon (11 Km) FEDL
тЧП Koregaon to Karad (48 Km)
- Leveling and Ballast work is in full swing till Masur
- Masur to Karad work at Average pace
- Work at Targaon,Rahimatpur,Masur and Shirravde at Good pace
тЧП Karad to Shenoli (13 Km)
- Ground Leveling work finally started and 50% Progress
тЧП Shenoli to Sangli (55 Km) FEDL
тЧП Sangli to Miraj (7 Km)
- Ground Leveling work completed till Vishrambag outer(After Vishrambag station)
- Ground Leveling Work is in Final stage from Vishrambag Outer to Miraj Jn
- Level Crossing will be eliminated and Tracks will come soon
Double Line :- 167 Km
Under Construction:- 112 Km
Around 59% Double line
Around 41% Line Under construction
please wait...Translate to EnglishUpdated now (Last update was on June 6, 2023)
Latest update as of July 13, 2023
Pune Miraj Doubling updates:
тЧП Pune to Shindawane (32 Km) FEDL
тЧП Shindawane to Ambale (9 Km)
- Ground Leveling work is almost done
- 2 out of 6 viaducts are completed
- 3 viaducts' foundation work is done and pillars are in progress
- One tunnel is almost complete
тЧП Ambale to Nira (43 Km) FEDL
тЧП Nira to Lonand (8 Km)
- Tracks are being laid
- Electrification work for the 2nd line is ongoing
тЧП Lonand to Adarki (17 Km) FEDL
тЧП Adarki to Wathar (10 Km)
- Ground Leveling work is finished (except at Wathar outer)
- New down platform will be added on the loop line
- Tracks are being laid
тЧП Wathar to Palsi (9 Km)
- Ground Leveling is done in some areas
- Ballast mountains are still not spread out in some areas
тЧП Palsi to Jarandeshwar (9 Km) FEDL
...
please wait...Translate to HindiAbhi toh update hua hai (pichhli update 6 June 2023 ko hui thi)
Update ab tak ka hai 13 July 2023 tak
Pune Miraj Doubling ke updates:
тЧП Pune se Shindawane tak (32 Km) FEDL
тЧП Shindawane se Ambale tak (9 Km)
- Ground Leveling ka kaam final stage mein hai
- 6 Viaducts mein se 2 viaducts ka kaam poora ho gaya hai
- 3 viaducts ki foundation ka kaam ho gaya hai aur pillars initial stage mein hain
- Ek tunnel final stage mein hai
тЧП Ambale se Nira tak (43 Km) FEDL
тЧП Nira se Lonand tak (8 Km)
- Tracks lag rahe hain
- 2nd line par electrification ka kaam chal raha hai
тЧП Lonand se Adarki tak (17 Km) FEDL
тЧП Adarki se Wathar tak (10 Km)
- Ground Leveling ka kaam ho chuka hai (Wathar outer mein abhi baaki hai)
- New Down PF Loop Line par banega
- Tracks lag rahe hain
тЧП Wathar se Palsi tak (9 Km)
- Ground Leveling ka kaam kuchh patches mein ho chuka hai
- Kuchh patches mein Ballast Mountains abhi tak spread nahi huye hain
тЧП Palsi se Jarandeshwar tak (9 Km) FEDL
тЧП Jarandeshwar se Satara tak (8 Km)
- Jarandeshwar taraf se koi progress nahi hai
- Satara taraf se thoda kaam dikh raha hai
тЧП Satara se Koregaon tak (11 Km) FEDL
тЧП Koregaon se Karad tak (48 Km)
- Leveling aur Ballast ka kaam Masur tak full swing mein hai
- Masur se Karad tak average pace mein kaam chal raha hai
- Targaon, Rahimatpur, Masur aur Shirravde mein kaam achhe pace mein chal raha hai
тЧП Karad se Shenoli tak (13 Km)
- Ground Leveling ka kaam ab finally shuru hua hai aur 50% progress hai
тЧП Shenoli se Sangli tak (55 Km) FEDL
тЧП Sangli se Miraj tak (7 Km)
- Ground Leveling ka kaam Vishrambag outer tak poora ho gaya hai (Vishrambag station ke baad)
- Ground Leveling ka kaam Vishrambag Outer se Miraj Jn tak final stage mein hai
- Level Crossing hataya jayega aur tracks jaldi aayenge
Double Line: 167 Km
Under Construction: 112 Km
Lagbhag 59% double line ban chuki hai
Lagbhag 41% line abhi construction mein hai