Defying Daunting Terrain, Linking Sikkim!
Sivok-Rangpo Rail Line Project🚉
Progress (As on 28.02.2023):
📈Overall...
more... Physical Progress: 53.2%
🪨Tunnel Mining works: 27.16 km
🏗️Piling work: 20111 m
🏗️Pier work: 526 m
🏗️Earthwork: 5.5Lcum
🌉Minor Bridge-5 nos
Source: MOR Twitter Handle