#update12
Electrification progress on Moradabad - kashipur - Ramnagar route
Moradabad - Got outer :- Electrification is complete.
Got outer - Sehal outer :- Foundation work complete, Poles erected, brackets placed and wiring done but not finalized.
Sehal...
more... - Kashipur outer :- Foundation work complete, Poles erected, brackets placed and wiring done & finalized.
Kashipur outer - Ramnagar :- Foundation work complete, Poles erected, brackets placed and wiring done but not finalized.
This is the progress of electrification on Moradabad - Ramnagar route.
SSP details:-
Pipalsana SSP completed
Roshanpur SSP completed.
Kashipur TSS work completed.
Ramnagar SSP work completed.
Got SSP completed
Note :-
Finalization of wiring going on.