#Mhow-Sanawad-Khandwa : Land acquisition required in full
length. 322.977 hectare land (15.99 Hect Govt. land + 208.9 Hect
forest land +98.087 Hect Pvt. Land). Acquired 54.72 ha (7.735 ha
govt +46.106 ha pvt.). Documents submitted to state Govt. and
land...
more... acquistion is in process.
Mhow - Mukhtiara Balwada ( 70.76 Km) Secion - Hilly Terrain,
diverted alignment & forest land involved. The quantity of land to
be acquired will be finalized after completion of FLS.
Mukhtiara Balwada –
#Sanawad (25.67 Km) :Land requirement
is 21.5 Ha (14.5 Ha Pvt and 7 Ha Govt. land). Land acquistion is
in process.
EPC tender for balance Civil, S&T and electrical/TRD is under
preparation.
Khandwa bye pass cabin -
#Khandwa (5 Km) : Work is in
progress. TDC : Dec.'22
Expected Completion for entire section: 2025-26 (In stages).
By WR
#akola