Kota - Bina Doubling Progress
A. Sogaria - Ruthiyai Section
1. MotiPura Chauki - Bhulon : CRS Inspection done on 30.06.2022
2. Bhulon - Chhabra Gugor : CRS Inspection done on 30.06.2022
3....
more... Chhabra Gugor - Kesholi
CRS inspection done on 13.12.2022
4. Kesholi - Salpura
CRS inspection done on 13.12.2022
B. Guna - Bina
only left section was Kanjiya - Pipraigaon, which is now ready to be inspected by CRS. loco trial has been done & NI Block is scheduled from 25.12.2022 till 05.01.2023.
C. Sogaria - Kota
expected to be commissioned by January (most probably by end of thus FY)
Bina Mahadeokhedi - Malkhedi : CRS Inspection done on 18.11.2022