SK (Deoghar) - Latest update on construction of platform number 3 & 4, construction of water filling work in trains and construction of Washing pit at Godda Railway Station.
(1) No platform number 5 as it was expected.
(2)...
more... No through-line between platform number 3 and 4 as it was expected earlier.
(3) Platform number 3 is about to complete.
(4) Platform number 4 is expected to be completed by the end of March 2022.
(5) Construction of water tank is completed. Pump is installed. Pipe work is not done.
(6) Construction of water-drain is completed.
(7) Construction of Washing-pit has been started. Right now, earth-filling is being executed.