First Time рдЦрдЧреЬрд┐рдпрд╛ рдХрд╛ рдЕрд▓реМрд▓реА рд╕реНрдЯреЗрд╢рди YouTube рдкрд░ред
#GroundReport 3rd Report on IRI
Dated : 19/08/2020
Video...
more... : Prabhat Sharan
Voice : Darbhanga Rocks
Khagaria - Alauli - Kusheshwar Sthan Rail Line Project
18 KM/42 KM
First Report :
10/10/2018Second Report :
07/05/2019 Khagaria - Alauli - Kusheshwar Sthan New Rail Line Project.
(KGG - KSS)
(Single Line With Electrification)
Total 8 Station. | 42 KM
1. Bishanpur
2. Kamathan
3. Alauli Garh
4. Chera khera
5. Shaharbanni
6. Tilkeshwar Halt
7. Sughrain
8. Kusheshwar Sthan Jn
ЁЯФ╖я╕П Approved :- 1998
ЁЯФ╖я╕П First Dead Line :- 2006/2009/2013/2016
ЁЯФ╖я╕П Actual Work Started :- 2007
ЁЯФ╖я╕П New Deadline :- 2020 (For 18 KM/Alauli)
Rest Unexpected.
ЁЯФ╖я╕П Cost (Previous) :- 162 Cr.
ЁЯФ╖я╕П Cost (Now) :- 544 Cr.
Connecting Line :- Hasanpur Road - Kusheshwar sthan - Sakri - Jaynagar/Darbhanga