#RVNL completed Railway Electrification of Dhuri-Jakhal (63 RKM/82 TKM) of Ludhiana-Dhuri-Jakhal section and Dhuri-Lehra Muhabbat (69 RKM/81 TKM) of Rajpura-Dhuri-Lehra Muhabbat section within target date. The electric loco speed trial was done successfully by CCRS at 120 Kmph.
All OHE/SP/SSP/TSS, high speed SCADA and electrical work has been completed. With this commissioning seamless operation of rail traffic from Ludhiana – Hisar – Rewari and Ambala -Bhatinda sections with electric loco has been achieved. The Oliver G test was done during inspection.
...
more...
Chief Commissioner Railway Safety inspected newly electrified 130km section & declared it qualified for train operations.
Source: