#ElectrificationUpdate #25November2019
DAL/DaliGanj Junction - STP/Sitapur Junction electrification update
Poles - 100%
Brackets - 99% done (Completion expected by 27-Nov-2019)
Wiring - Currently wiring happening at STP/Sitapur station leaving one patch where BUW-STP-ROZA section...
more... existing line crosses DAL-STP line another patch at DAL yet to get connected in existing line. Rest all is done.
OHE van : Started from DAL end and completed till KMP/Kamlapur.
SSP - 2 SSP's been located at SD and STP. At STP basic structure completed and two fuses has been placed (Completion expected by Dec2019 or so). At SD nothing much progressed.
SP - Basic structure completed and two transformer has been placed at BKT SP (Completion expected by Dec2019 or so).
Block - 4 hours block been requested at DAL and STP respectively for connecting with existing live wire. More info awaits.
OHE wire energized - Expected by Dec2019
Trial run : First trial run expected on 29-Nov-2019 which depends on following :
1. Wiring completion at STP
2. OHE finalize work till STP
3. Block completed for connecting new line with existing live wire
else it would be in month of Dec2019.
CRS inspection - As per newspaper 25-Dec-2019
Commercial uses - Any point of time after successful CRS and permission granted by traffic department.
** All completion dates are tentative**