Status of Rail Route between Bishnupur to Arambag as on 30/09/2019 as per the project summary report by Eastern Railway.
"The main work Tarkeshwar – Bishnupur (82.47 km) – New line - Work was sanctioned in 2000-01 and cost of the project is Rs 480.68 Cr. Tarkeshwar –Goghat (33.94 km) New line – Commissioned on 06.03.2016 Mayonapur – Bishnupur (22.68 km) New line – Commissioned on 16.09.2012 Section Goghat – Kamarpukur (5.50 km) was completed during 2018-19 except 950m stretch where the work is stopped by local villagers at Bhabadighi pond. State Govt. is pursued repeatedly. Balance section Kamarpukur - Mayonapur (20.35 KM) falling 3.3Km for Hoogly district and 17.05 Km is in Bankura district. In Hoogly district(3.30km)—0.755 Km handed over to...
more... Rly. and balance 2.545 Km land acquisition done but compensation has not been distributed. In Bankura district(17.05)—8.245 Km handed over to Rly. and balance 8.805 Km land acquisition done but compensation has not been distributed. Remaining 3.126 KM, land Acquisition is under processed. "