Spotting
 Timeline
 Travel Tip
 Trip
 Race
 Social
 Greeting
 Poll
 Img
 PNR
 Pic
 Blog
 News
 Conf TL
 RF Club
 Convention
 Monitor
 Topic
 #
 Rating
 Correct
 Wrong
 Stamp
 PNR Ref
 PNR Req
 Blank PNRs
 HJ
 Vote
 Pred
 @
 FM Alert
 FM Approval
 Pvt
Forum Super Search
 ↓ 
×
HashTag:
Freq Contact:
Member:
Posting Date From:
Posting Date To:
Blog Category:
Train Type:
Train:
Station:
Pic/Vid:   FmT Pic:   FmT Video:
Sort by: Date:     Word Count:     Popularity:     
Public:    Pvt: Monitor:    Topics:    

Search
  Go  
dark modesite support
 
Fri May 3 23:40:08 IST
Home
Trains
ΣChains
Atlas
PNR
Forum
Quiz
Topics
Gallery
News
FAQ
Trips
Login
Post PNRPost BlogAdvanced Search

Blog Entry# 4380759
Posted: Jul 18 2019 (11:28)

No Responses Yet
1 Followers
General Travel
3302 views
1

Jul 18 2019 (11:28)  
ForeverRailfan^~
ForeverRailfan^~   53152 blog posts
Entry# 4380759              
Distribution of Funds (Rs. 375 Crore Total) under Sanctioned Umbrella Works for Electric Loco Sheds/Outpits
21 SR AJJ 1 3190.00 AUGMENTATION OF CAPACITY FROM 120 TO 175 LOCOS. HOLDING INCREASED TO 174 IN APR 2015. AUGMENTATION PROPOSED SINCE PWP2015-16, YET TO BE SANCTIONED. PROPOSED COST IN PWP2019-20 ? 31.9 Crores.
22 SR RPM 1 1950.00 PRESENT HOLDING 89+5(UNDER COMMISSIONING). 11 MORE allotted to be homed in RPM. Hence, it is proposed to augment infrastructure, to increase holding from 100 to 120 locos.
23 SER SRC 1 3500.00 100
...
more...
Cr. are needed for increasing homing capacity to 175. In Phase-I, 35 crores have been asked to home 100 locos (present holding 106). Needed urgently to maintain coaching link of SER.
24 SER TATA 1 2800.00 Shed already has around 250 locos against homing capacity of 150. Due to congestion under repair of this shed remains high. Moreover the shed has to provide around 50 WAG-9 MU and 20 pair of DPWCS.
25 SER TATA 1 500.00 CTRC/TATA repairs wheel set and TM for SER as well as other Rlys. Rs. 11 Cr.are needed for its modernization. In phase-I, Rs. 5 Cr. are needed to start rewinding of stator of 3-Phase Traction motor.
26 SER BKSC 1 2000.00 Rs. 34 Crore are needed for increasing its capacity to 150 locos (present holding 145). In phase-I Rs. 20 Cr. are needed to home 125 locos including 3-phase locos and to start IOH within shed itsself.
27 ECR MGS 1 3000.00 ELS MGS is already maintaining 221 locos and whereas the present infrastructure is only for 150locos. For smooth maintenance of electric locos capacity augmentation from 150 to 200 locos are required.
28 WCR TKD 1 1500.00 The present holding is 237, further locos are allotted and shed holding capacity is 175 only. Hence there is infrastructural crisis. Augmentation shall enable the shed to increase its out turn.
29 WCR NKJ 1 1662.00 Holding of shed is 215, Holding will reach 250 in near future fund is required to acquire requisite homing facility for 250 and 3 phase locos
30 ECR GMO 1 7864.00 ELS GMO is maintaining 280 nos. of conventional as well as 3 phase locos and likely to exceed 300 soon. it is the main feeding shed for coal loading At present capacity of ELS GMO is 120 only.
31 WCR ET 1 3579.00 Holding of shed is 196, Holding will reach 250 in near future fund is required to acquire requisite homing facility for 250 and 3 phase locos and drop pit table
32 NCR CNB 1 1977.00 Current infrastructure of the shed is for homing of 175 locos. Present holding is 225 locos. There is crisis of requisite infrastructure in the shed. Hence, it is proposed to augment the capacity of
33 ECoR ANGL 1 4609.91 ELS/Angul holding was 196 locos against sanctioned capacity of 200 locos. Besides, 25 nos. new 3-phase locos are being allotted by Rly. Board. Hence it is proposed to enhance the facility at ELS/An
34 ECoR WAT 1 4147.84 Present holding of ELS/VSKP is 286 locos, against sanctioned capacity of 200. Besides, new 3-phase locos are being allotted regularly by Rly. Board. Hence it is proposed.
35 NCR JHS 1 1725.00 Current infrastructure is for homing of 175 locos. Present holding - 217 locos. Augmentation of the capacity needed from 175 to 200 locos. Proposed cost in PWP 2019-20 is Rs. 17.25 Cr.
36 ECoR ANGL 1 1058.99 ELS/ANGL has no laboratory for testing electronic component and cards of WAG9 locos, thereby in case of any component failure, locomotive is get detained at shed. No alternate arrangement is available
37 WR BL 1 100.00 Augmentation of existing facilities for increasing homing capacity from 125 to 200 locos. At present holding 199 Electric locomotives.Proposed in PWP 19-20 Ph_42
38 NR GZB 1 250.00 Re-flooring and epoxy flooring in shed along with horticulture in surroundings and re-location of main entry gate of the shed - To improve deteriorated flooring in shed / improve approach & ambiance
39 NR GZB 1 200.00 Effluent Treatment Plant (ETP) along with improvement in drainage - Required for shed waste water treatment and rain water harvesting system.
40 NR GZB 1 200.00 Augmentation of wheel shop for bringing flow in machines - To augment infrastructure to facilitate movement of men and material flow from one machine to another machine
41 NR LDH 1 100.00 Facility of cleaning of cyclonic filters - To facilitate cleaning of cyclonic filters of three phase locos as per RDSO SMI no. 0286
42 NR LDH 1 150.00 Extension of Main building of TM & bogie section toward station end (29.5x22m)-ELS/LDH holding has increased to 195 & likely to increase further. Existing space is not sufficient to overhaul bogie& TM
43 NR LDH 1 200.00 Effluent Treatment Plant (ETP) along with improvement in drainage - Required for shed waste water treatment and rain water harvesting system.
44 NR KJGY 1 400.00 Provision of addl track of 800 m length with land acquisition to facilitate movement of loco to and from yard - Due to congestion in KJGY yard, a dedicated line is needed to receive and turn out loco
45 NR KJGY 1 100.00 Infrastructure for storage of UES and handling equipment - Newly established shed needs various stacking arrangements and stands for various loco equipment and material.
46 NR KJGY 1 200.00 Effluent Treatment Plant (ETP) along with improvement in drainage - Required for shed waste water treatment and rain water harvesting system.
47 NR Outpit 1 1000.00 New Delhi-Augmentation of facilities in trip sheds & washing lines at New Delhi for MU and Push pull operation of trains- To create facilities for maint. of MU locos in trip sheds/ washing line ends.
48 NR Outpit 1 100.00 Augmentation of outpit at ASR - With electrification, number of electric locos requiring attention has increased
49 NR Outpit 1 100.00 Improvement of outpit at JAT - Condition of the out pit is bad.
50 NR Outpit 1 200.00 Augmentation of outpit at ELS/GZB - With increasing holding attention of locos at outpit has increased and therefore need augmentation wrt to number of pits and covered shed
51 NR Outpit 1 100.00 Augmentation of outpit at ELS/LDH - With increasing holding attention of locos at outpit has increased and therefore need augmentation
52 NR Outpit 1 100.00 DBSI - Improvement in civil infrastructure along with electrical power supply - Old established workshop require renovation to suit works for electric loco
53 NR GZB 1 700.00 Augmentation of holding capacity from 200 to 250 locos - ELS/GZB has a infrastructure capacity to home 200 locos. Holding is expected to reach 250 soon. Augmentation of holding capacity is required.
54 NR LDH 1 800.00 Augmentation of holding capacity from 175 to 200 locos - ELS/LDH has a infrastructure capacity to home 175 locos. Holding is expected to reach 250 soon. Augmentation of holding capacity is required.
55 SECR BIA 1 700.00 1. Setting up of Stores Depot facility at ELS BSP and augmenting at ELS-BIA.cost Rs.500Lacs. 2.Setting up Shed & Building Management System as staff efficiency multiplier at ELS BSP&BIA. Rs.200Lacs.
56 CR BSL 1 6342.00 Augmentation of shed from 176 to 200 locos and creation of facility for homing of three phase locomotives at ELS/BSL.Proposed in PWP-2019-20.Yet to be sanctioned.
57 ECR Outpit 1 200.00 DHN- Provision of covered shed for electrical loco trip shed at Dhanbad.
58 CR Outpit 1 611.00 Provision of two extra line at electric loco trip shed Vidyavihar for carrying out trip examination of electric locos. More number of trains likely to run with electric loco on electrification of KRCL
59 CR AQ 1 528.00 Provision of shunting and testing line facility and extension to inspection Bay shed.
60 CR AQ 1 561.03 PROVISION OF SHUNTING AND TESTING LINE FACILITY AND EXTENSION TO INSPECTION BAY SHED AT ELECTRIC LOCO SHED, AJNI, NAGPUR
61 SCR BZA 1 1185.00 Acute shortage of loco wheel sets was discussed in a meeting held by AGM/SC with PCEE and PCME and it was decided to develop wheel shop facilities at ELS/BZA. These facilites are essential.
62 SCR KZJ 1 760.00 3 phase locos maintenance facilities are proposed to develop at ELS/KZJ. Minor civil works costing one Crore and M & P required are now proposed.
63 WR BRC 1 50.00 Electric loco shed Vadodara-Renovation of old shed and Improvement in Infrastrucutural facilities. Total cost of this work is Rs. 5.08 Crs. This work proposed in PWP 2019-20
64 CR Outpit 1 1928.00 Electric Locomotive Workshop Bhusawal - Improvement of maintenance facility and rehabilitation of infrastructure facility.
65 SCR LGD 1 1016.00 Augmentation of homing capacity of 200 to 225 locos proposed. Present holding is 234 locos.Proposal submitted during 2016-17, 17-18,18-19,19-20.
66 SECR BIA 1 300.00 Provision of Important M&P, Heavy equipment storage space for clearing shed floor area and essential staff amenity at ELS BSP Rs. 300 Lacs.
67 CR KYN 1 7722.00 Augmentation of ELS/Kalyan by Creation of facilities for homing of 200 locos. The present holding of ELS/Kalyan have already been increased to 230 locos.
68 WR Outpit 1 100.00 Laxmibai Nagar(Div-RTM)-Provision of electric loco trip shed.Total cost of this work is Rs. 10.68 Crs. This work proposed in PWP 2019-20 under PH-42.
69 WR Outpit 1 100.00 Provision of trip shed in newly electrified section of Western Railway at Rajkot(RJT).
70 WR Outpit 1 100.00 Provision of Electric loco trip shed at HAPA (Div-RJT) in newly electrified section of Western Railway.
71 WR Outpit 1 100.00 Provision of Electric loco trip shed at Bhavnagar(Div.-BVP)in newly electrified section of Western Railway.
72 WR Outpit 1 100.00 Provision of Electric loco trip shed at Chittaurgarh-COR (Div-RTM) in newly electrified section of Western Railway.
73 WR Outpit 1 100.00 Provision of electric loco trip shed at Gandhidham-GIM (Div-ADI) in newly electrified section of Western Railway.
Total Funds Demanded-72566.77
SOURCE : click here

Translate to English
Translate to Hindi

Travel SAFE

1. RailFanning does NOT MEAN dangerous pics/videos.
2. Doorplating pics/youtube videos are strictly FORBIDDEN in IRI.
3. Take plenty of food pics and other safe pics.
4. Write human interest narratives to make the pics interesting.
5. Enjoy blogging and travelling SAFELY.

REMEMBER: YOUR LIFE is the most precious thing, NOT RailFanning.

Leading Polls

Rail News

New Trains

Site Announcements

  • Entry# 5648027
    Mar 01 2023 (12:44AM)


    In response to past confusions with Train/Station updates and resulting fights and controversies, the following clear and objective guidelines are being issued, with no room for any arguments or debates about validity. Also, included, some other changes with respect to Ratings. 1. All Red Ratings will require further explanation. Red Ratings won't...
  • Entry# 5388512
    Jun 24 2022 (08:45AM)


    As announced previously, there are a few changes coming to IRI user accounts, based on past practices. 1. As before, you will be able to quickly DELETE your IRI User account at ANY time. However, the menu option for this was hidden in the profile page, and could not easily be located....
  • Entry# 5148000
    Nov 29 2021 (06:40AM)


    A new feature will be released soon, whereby you can follow blogs tagged with specific Trains & Stations. If you have already posted blogs tagged with some Train/Station, then you will be set to automatically follow that Train/Station. Thereafter, any future news/blogs tagged with those Trains/Stations will be marked to your...
  • Entry# 5093784
    Oct 13 2021 (07:04AM)


    These days, every other day, we are getting requests from members to allow email login to their FB-based IRI account. 10 years ago, we had given the option for users to login through FaceBook - in retrospect, this was a mistake. These days, apparently, users are quitting FaceBook in droves because...
  • Entry# 4906979
    Mar 14 2021 (01:12AM)


    Followup to: Fmt Changes The new version of FmT 2.0 will soon be here - in about 2 weeks. As detailed in the previous announcement, many of the old FmT features like Train TT, Speedometer, Geo Location, etc. will be REMOVED. It will be a bare-bones simple app, focused on trip blogging. It...
  • Entry# 4898771
    Mar 06 2021 (10:33PM)


    There are some changes coming to FMT. Many of the features of FMT, like station arrival, TT, speed, geo, passing times, station time, etc. are ALREADY available in OTHER railway apps. So all of these features will be REMOVED. We'll have ONLY BLOGGING - quick upload of pics/videos/audio, etc. You may attach...
Scroll to Top
Scroll to Bottom
Go to Mobile site
Important Note: This website NEVER solicits for Money or Donations. Please beware of anyone requesting/demanding money on behalf of IRI. Thanks.
Disclaimer: This website has NO affiliation with the Government-run site of Indian Railways. This site does NOT claim 100% accuracy of fast-changing Rail Information. YOU are responsible for independently confirming the validity of information through other sources.
India Rail Info Privacy Policy