Jaipur- Phulera Electrification
1. Pic 1 - 4 jaipur outer t kanakpura 80% poll are Fixed
2. Kanakpura Station - Poll are not Erected
3. Kankpura to Phulera janction 95% Polls are fixed
4....
more... Bindayka to Hirnoda Outer (jaipur side) mask & insulator are fixed
5. pic 5 Bindayka to Phulera all station 95% cross beam are fixed
6. vid. 1,2 Bobas outer (jaipur side) to Asalpur Jobner Outer Wiring complete.
7. vid. 3 AsalpurJobner Outer (phulera side) to dinda Station outer wiring complete
9. vid 4 phulera outer to Hirnoda
10. vid. 5 Phulera junction Elecrification