Harlapura-Binkadkatti 23kms Doubling Update part of Hosapete-hubballi-vasco Doubling :
*Btn HPT-UBL 143 kms ,120kms line already doubling completed & opened for traffic .
*only this 23kms section doubling work is left. which is likely to get complete in next 6 months.
pics
1....
more... Just after harlapura where doubling work going on
2.near Kanaginahal
3.near kanaginahalu LC
4.Kanaginahal New FOB under construction
5. kanaginahal 2nd PF under construction
6&7 Gadag outer Hpt side 95% Ground leveling work completed for 1km without rly track.
8.Looks like new FOB under construction at GDG.