Hosapete-Bhanapura 40kms Double Electrification Update part of HOSAPETE-HUBBALLI-VASCO RE PROJECT:
* Poles are Erect Btn HPT-Ginigere but wiring not started .
*wiring work completed btn GINGERE(Excl)-Koppal (KBL) -124.6km-119.6km.
*Poles are Erect Btn Koppal-Bhanapura(Excl) but wiring not started .
*HPT(Excl)-Bhanapura(incl)...
more... 40kms RE was Target to complete by Q1 of 2019-20
pics
1.HPT outer Poles are Erect but wiring not started.
2.TB River new bridge RE not started
3&4 At Munirabad
5.At Hitnal new PF under construction
6&7.At Ginigere wiring vehicle parked at here
8&9 wiring work completed btn GINGERE(Excl)-Koppal (KBL) -124.6km-119.6km
10. SSP under construction at KBL
11. portal At Koppal
12.Just before Bhanapura
13. after Bhanapura few poles are placed but not fixed.
14. RE poles dumped at Harlapura.