Pics taken at city station about work of UDZ-AII Electrification & UDZ-HMT GC.....
1. Electrification work towards RPZ side. Poles
installation pending on platform no. 1.
2-3. Wiring completed on platform no. 3 & 4 and pending on platform no. 5.
4-9....
more... Maharaja Express standing on platform no. 3 & UDZ-MYS humsafar on platform no. 5.
10-11. Solar Panel system installed on newly built platform no. 4 & 5.
12-13. Umra railway line finally linked with main line of city station.
14-18. Track of platform no. 4 & 5 and 1 additional line is yet to be connected towards umra main line, sleepers have been layed and track linking is pending.
19-24. Ballast supply completed towards Umra side main track and others loop lines.
25-26. Ending point of electrification towards Umra side.
27-28. Extension work of new washing line towards Umra side is going on. No sign of extension of old washing line.
THANK YOU...