Ya today I visited again bgp station which I do on daily basis being near to home all poles has fixed only 3-4 connector left to connect two platform Hookes fixing work has just begun not only till Sultanganj everything is complete till Muslim school Bhagalpur crossing 800m away from railway station, all wiring done.Only question remain about if electrification of tunnel completed? And other one is progress of substation from Jamalpur to BhagalpurJn ?without which electric train will not start even if wiring completed.Has the Kiul to danauri wiring completed as when I passed on 18 Dec that part was left for wiring and what about wiring between sarobag to Jamalpur wiring.
Also towards Kahalgaon side till the end of yard...
more... at BhagalpurJn digging of holes and cementing it is being carried out on mass scale.
Looks if substation starts functioning on time than we will see E Locos by March onwards.