22-Oct-18
12394
Dir 55
NR DLI
30623 GZB WAP7 3-Phase
DOC,...
more... GZB, Jun 13 2018 / IB, GZB,
Sep 21 2018 Brake system (E-70/Knorr)
.
(NDLS-RJPB, Load- 21 Coaches), late start Ex NDLS station for fault message on DDS " "Fault in brake electronics" and BP pressure dropped to 1.5 kg/cm2. Fault acknowledged, VCB closed but BP not charging more than 1.5 kg/cm2. VCD, Air drier isolated. MCE Off/On but not succeed. Closed and open BP/FP angle cock toward load side than ok. Build up pressure and started. IGBT loco, Brake system- FTIL, IC'0'-05.03.18, IB-21.09.18, Section- NDLS station, Sch dep- 17.25 hrs, Act dep- 18.20 hrs.