Gangavathi railway station update: after 14months ..I visited this station very less progress happened ...
1.there r 3 pfs + 1 extra track load point for goods train total 4 tracks
2. track laying up to pf end (karatagi side end ) completed successfully..but after pf end some track alignment need to be done specially for loco reverse for about 200-300mts ...about 1km single line from ggvt track laid without proper alignment..
3.Fob...
more... work almost completed..concert work completed..finishing work to be done
4.ties for pf on 3 pf karatagi side 50%completed still 50%remaining gingera side yet to start ties work .
5.inside station ties work completed
6. Wiring going on and pipe lines almost completed
7.grills & wedding work going on slowly
8 .shelter for pfs not yet covered and no sb board nor lighting work started .
9. Road connectivity to station under progress
10.rly quarters work construction
Finally chance are there to run passenger train by December if fail then in February 2019 for sure ..but to complete building work it 'll take 5-6months more ..work is slow ..no chance for train up to karatagi for next 2 years ..