Work on two smaller stations in the city — Guru Tegh Bahadur Nagar and Chunabhatti — will also begin soon. The upgrade of the two stations on the Harbour line, as part of the Prime Minister's Monitored Project of laying the third line between Wadala and Kurla, has slowed down due to delay in shifting of slums along the stretch. This is the same project in which Kurla station's Harbour side will be elevated, segregating the goods and the Harbour line.
Work has already begun at various stretches where...
more... there are no encroachments and no technical issues. While pillars for the deck are coming up at a rapid speed, preparatory work has begun on making space for the third line at Chunabhatti and GTB Nagar stations," a senior railway official said. "There were about a 1,000 structures that the state government needed to relocate, and the process has been taking time."
At GTB Nagar station, existing middle platform will be moved ahead on the north side with additional platforms on either side, making space for a third line