Gadag - Hotgi Doubling updates.
-
-
Bhima River bridge
-
The...
more... approach and after the bridge, the land levelling work is done.
The pillars of the bridge have been constructed.
Girders launching - the toughest part - is yet to start.
From the size it looks like it will be a double line bridge.
Some work is going on at one end, but since this section is not for this year not much pace.
-
There are other works related to stations going on in this section, which I will post in subsequent blogs.
-