HOSAPETE -GUNTAKAL double electrification update part -1 from HPT upto KAR/A.P..
1.Hosapete - kariganuru =7km - work not yet started ,progress nil.
2.kariganuru - pk halli=6km - pic 1 foundation for poles just layed.
3. also track renovation going on along hpt-gtl pic2.
4....
more... old sleeper bed are dumpped at pk halli st pic 3.
5.electric poles are placed at pk halli st for fixing pic 4.
6.pk halli -toranagallu =20km pic5 concrete cement done in pole hole.
7.toranagallu -daroji- kudatani=13km pic 6 &7 erected electric poles r been fixed.
8. kudatani- ballari =20km -sadly work not yet started ,no progress.
9.swr zone limits ends , scr zone begins pic 8.
10.ballari - haddinagundu-hagari =15km few places foundation for poles has layed pic 9 &10.
11. hagari-virapura=8kms - electric poles fixed with extended wings after hagari pic 11 and workers are working to fix it pic 12.
12.karnataka limit end ...kar/a.p border pic13..
priediction : karnataka part ie from a.p border upto ballari (excl bay) can be complete by SCR within dec 2018 or if not by march 2019.but swr side from bay upto hpt atleast we have wait upto march 2020.
Note :1)part 2 to be continued in another post blog.due over load of pics and due to end of karnataka /swr part.
2) shortly i'll upload full video after editing .
picture credit : all photos are captured by my self.