#ElectrificationEntry# 3128126
/blog/post/3128126Entry# 3436818
/blog/post/3436818
-----
Delhi - Rewari - Jaipur Electrification:
Jul 2018 Status
-----
In DEC Delhi Cantt. Rly Station, Fixing Portals, Single Poles, Crossbeams WORKS ONGOING
PF 4, 5 Portals are fixed
PF 1,2,3 Portals are not found
No wiring in DEC Delhi Cantt. Rly Station
Delhi Cantt. Rly Stn - Patel Nagar - Delhi Sarai Rohilla
Poles and Portals fixed about 50%
No Wiring
-----
DEC Delhi Cantt. Rly Stn
--
Elec foundation works finished
Elec Poles are FIXED to foundation 80%
Elec Portals are FIXED to foundation 60%
Crossbeams for Elec Portals FIXED 0%
Elec Poles/ Portals where cantilever assembly FIXED 0%
Wiring completed 0% NO WIRING in Station
-----
DEC Delhi Cantt. Rly Stn - PTNR Patel Nagar
--
Elec foundation works finished
Elec Poles are FIXED to foundation 70%
Elec Portals are FIXED to foundation 70%
Crossbeams for Elec Portals FIXED 0%
Elec Poles/ Portals where cantilever assembly FIXED 0%
Wiring completed 0%
-----
PTNR Patel Nagar - DEE Delhi Sarai Rohilla Rly Stn
--
Elec foundation works finished
Elec Poles are FIXED to foundation 50%
Elec Portals are FIXED to foundation 50%
Crossbeams for Elec Portals FIXED 0%
Elec Poles/ Portals where cantilever assembly FIXED 0%
Wiring completed 0%
---------------------