News source : Internal (L&T engineers and NER railway officials)
News : L&T was ready to finish rest of the work on ASH/Aishbagh - STP/Sitapur gauge conversion however NER hasn't release budget so work was on hold. Last week good budget has been released and work already been resumed and its expected that all basic work i.e. track, signaling, NI etc including all mega blocks will be completed by 31-May-2018 however station building construction will be on going even after CRS too. As on date L&T along with NER planning to finish basic infrastructure by mid of the Jun;2018 and same time trying to do trial run too. If all goes well by Jul;2018 CRS is planned and commencement can be...
more... done post successful CRS.