RMV to GDV up to indupalli bed works done indupalli to gdv no work started
GDV TO MDVL after OTR to MDVL bed works done and Full MDVL station going to be new station buldings cnstrn going on
MDVL-KKLR this was the strech full works done except wiring poles laid on both lines
KKLR-AKVD track laying done...
more... upto PLVA after PLVA gravel placed and even rails and at kolleru bridge pillers workesgoing on after bridge bed works done till AKVD AKVD-BZA to wards bza was new line down line was old one FROM AKVD towards ns line was new one
AKVD-BVRT bed works done and bridge on venkahai canal pillers done
BVRT-BVRM no works started it was tough strech 2 bridges and in town and 2junctions
BVRM-VVM from PAGM to vvm bed works done and pf cnstrn at SGKM even at vvm
VVM-PKO bed works done at VVM bridge construction going on