Finally the long wait is over..
*Kashti-Daund-Hadapsar is energized with 25KV AC charge From Today..
*Hadapsar-Ghorpadi may be made live Before 15 July..
*CRS Inspection will happen After 20 July..
*If all things go...
more... as per plan, by 01-Sep-2016, goods trains will start plying with E Locos!
And further, by 01-Nov 2016, Exp Trains will start running with E Locos!!!