Sabse pehle Ajmer se beawar ke beech no sign of doubling.....
Phir beawar se Haripur tak thoda work Haripur side Hua Hai...
Haripur se marwar jn tak sirf tracks ke upar aggregates daalna baaki Hai , sojat ke pass bridge ke do deck tyaar nahi Hua Hai.....is route Mein 90% work complete Hai...bas stations ka renovation ho raha Hai..sojat pe toh 2 nd platform ekdum final stage pe Hai...kyuki 4 tracks toh pehle hi the..
Marwar...
more... jn to rani no progress..
Rani to jawai bandh full work done except some stations renovation especially falna aur rani ka hona baaki Hai..
Jawai bandh se moribera tak earth work ho raha Hai..
Moribera se swaroopganj tak operational Hai track..
Swaroopganj se morthala tak all done but no trains r running on that track..
Morthala se abr no progress..