Electrification work in going on.
BWN - BHP = Poles erected in almost all stations, straightening of wires is going on.
BHP - Ahmadpur - Poles erected , but wires not straightened in all stations.
Ahmadpur- SNT = Sainthia fully ready !
SNT...
more... - RPH = Poles erected, wires hanging is going on.
RPH - Pakur = Same as in SNT - RPH section
Pakur - Nfk - Incomplete, poles erected upto Tilbhita.
Nfk - Malda = Materials stacked only.