# Details of Neora (NEO) - Jatdumri (JTDM) - Daniyawan (DHWN) - Bihar Sharif (BEHS) - Sheikhpura (SHK) rail line
✓Approved :- 2002-03
✓Length :- 123.2 km
✓Termini :- NEO, SHK
✓Status...
more... :- partially operational
•opened - 2015 [DHWN - BEHS section]
•electrified - 2019 [DHWN - BEHS section]
✓Deadline for complete line commissioning - March 2023
✓ Sections :-
(a) Neora - Daniyawan (42.2 km)
~ Neora to Jatdumri - 18.4 km
~ Jatdumri to Daniyawan - 23.8 km
Status - Underconstruction
Deadline - 31st December, 2022
(b) Daniyawan - Bihar Sharif (38.28 km)
Status - Operational (2015)
(c) Bihar Sharif - Barbigha (25.9 km)
Status - Underconstruction
Deadline - March 2022
(d) Barbigha - Sheikhpura (16.8 km)
Status - Partially commissioned~ Sheikhpura to Sarsa Jamalpur till 1 km before Barbigha (15 km)
Deadline - March 2022
✓ Stations enroute
# Neora [NEO] ~ 0 Km Terminal | PNBE - DNR - DDU line
# Ganpura (crossing station) ~ 8.3 km
# Bajidpur Halt ~ 14.4 km
# Jatdumri [JTDM] ~ 18.4 km | PNBE - GAYA line
# Maranchi Halt ~ 21.4 km
# Fazal Chak (crossing station) ~ 27 km
# Gawaspur halt
# Sarthua (crossing station) ~ 37 km
# Daniyawan Jn [DHWN] ~ 42.2 km | FUT - NES - TIA line
# Sultanpur Gram[SLNG] ~ 48 Km
# Lachhubigha (crossing stn) [LUBA] ~ 51 km
# Rukhai Halt [RUKH] ~ 56 km
# Chandi (Crossing stn) [CNDI] ~ 58 km
# Badhauna Halt [BADH] ~ 62 km
# Noorsarai (Crossing stn) [NRSI] ~ 66km
# Dekpura Halt [DKR] ~ 75 km ~ also part of BKP - TIA line
# Sohsarai Halt [SOW] ~ 77 km ~ also part of BKP - TIA line
# Bihar Sharif Junction [BEHS] ~ 80.4 Km | BKP RGD - NES - TIA line
# Nepura [NEPRA] ~ 89 km
# Asthawan (crossing stn) [ATWN] ~ 93 km
# Amanwan Halt [AMNWN] ~ 101 km
# Barbigha Station [BRBGH] ~ 106.4 km
# Sarsa Jamalpur (crossing stn) [SSJMP] ~ 111 km
# Matokhar Halt [MTKHR] ~ 118 km
# Sheikhpura Junction [SHK] ~ 123.2 km | GAYA - KIUL line