Deedwana-Piplai(32.51 km) section :-
Balance Part of Dausa-Gangapur city (92.67km) New Line project
•Earthwork done during the month – Nil, cumulative progress – 22,31,000 cum out of total 22,60,000 cum.
•Blanketing done during the month – Nil, cumulative progress – 2,19,000 cum out of total 2,21,000 cum.
...
more... •All major bridges completed.
•Minor bridges completed during the month – 2 Nos, cumulative progress – 14 out of total 15.
•ROB/RUB/LHS completed during the month –Nil, cumulative progress – 33 out of total 45.
•Ballast supply completed during the month –Nil, cumulative progress is 60,000 cum out of 1,12,000 cum.
Last update : 9 July 2021
TDC : June 2022
please wait...Translate to HindiDeedwana-Piplai(32.51 km) section :-
Dausa-Gangapur city (92.67km) New Line project ka baki hissa
• Mahina mein koi kaam nahin hua, jama hua progress hai - 22,31,000 cum total 22,60,000 cum se.
• Mahina mein koi blanketing nahin hui, jama hua progress hai - 2,19,000 cum total 2,21,000 cum se.
• Sabse bade pul poore ho gaye hain.
• Mahina mein chote pul 2 hua poore, progress hai - 14 total 15 se.
• ROB/RUB/LHS abhi tak nahin hua, progress hai - 33 total 45 se.
• Ballast supply abhi tak nahin hui, progress hai - 60,000 cum total 1,12,000 cum se.
Last update : 9 July 2021
TDC : June 2022