#UDNJLdoubling
Full update of #UDNJLdoubling plus Electrification Report
> Udhna - Niyol = no sign of Earth work
> Niyol - Vyara = Earth work Started Bridge work completed OHE pole installed
>...
more... Vyara - Ukai Songadh = Double line started
> Ukai Songadh - Chinchpada = Doubling plus electrification completed waiting for CRS approval
> Chinchpada - Nandurbar = Work getting close to complete
> NAndurbar - Dondaicha = No sign of Electrification
> Dondaicha - Amalner = Earth work completed in some place OHE pole also installed
> Amalner - Dharangaon = Double line started
> Dharangaon - Paldhi = Track work started OHE pole installed
> Paldhi - Jalgaon = no sign of Earth work