The doubling work at KDGH is in full swing.
Result: First time ever I have seen a ticket counter being operated in an iron container instead of a brick wall room.
Not sure if many here would have seen such incident earlier.
Due to the doubling work, the existing concrete structure & Pf 1 have been completely demolished to make way...
more... for the second track in place of it.
The new building is under construction (Can see in Pic 2, Down on the PF) on new PF 1 and Pf 2 is under construction adjacent to the new line that being laid in the place old PF 1.