Cost- ₹ 2449.91 Cr.
💰 Expenditure till date- ₹ 1035.70 Cr.
🟢Overall Physical Progress- 40%
🔘Length- 279.28 Km.
🔘Length commissioned- 93.95 Km
🔘Remaining- 185.33 Km
🔘Land acquisition completed- 76.27/ 99.25 Hectare (76.84%)
A) Completed Sections: 93.95 Km (33.64%)
🔘Kohli- Chichonda
B) Near Completion Sections- 11.68 km (4.1%)
(Likely completion this year)
🔘Kohli- Kalmeshwar
C) In Progress Sections- 191.42 km (68.54%)
🔘Chichonda – Itarsi
🔘Nagpur – Kalmeshwar
🟢Completed Works-
☑Earthwork Including Blanketing- 44/103 Lcum (43%)
☑Important Bridges- 3 in Progress
☑Major Bridge + Rail Over Rail Bridge- 12/34(36%)
☑Minor Bridge/RUB- 89/382 (23%)
☑Station Building- 9/30 (30%)
☑Track linking- 80/280 Track km (28%)
☑Overhead Equipment OHE Foundations- 1066/6666 (16%)
☑OHE Mast Erections- 970/6060 (16%)
☑OHE Wiring Track km- 50/280 (17%)
🔴Completion of this new 3rd line will reduce congestion of Nagpur – Itarsi – Bhopal busy route and will improve mobility of the trains.
🔘Progress of doubling/3rd/4th lines all over Central Railway’s 5 divisions-
🔘CR has completed 147.77 km multitracking (new line/doubling/3rd/4th line) in current FY from April 2023 till date 2023.
🔘3886.95 Crs planned by CR in this year for new lines/doubling/3rd/4th line.
🔘2983.47 Crs expenditure done till date.