My friend's RTI regarding PSRs, speed trials and DMA KPK doubling to Adra.
Item No : 1- Permanent speed restriction of 15 KMPH at Anara and of 80 KMPH at Bero end of Ramkanali exist according to respective sharp reverse curves. Elimination of PSR at ANR has been sanctioned and included in DPR of Chandil Burnpur 3rd line. New alignment at Ramkanali is being planned with Engg/DEN/North and DFCCIL to remove restriction.
Item No : 2-130 kmph trial between Chandil and Anara has been successfully conducted. Track oscillation was found satisfactory. Complete...
more... OHE renewal order issued in view to reduce resistance, heat and corrosion alongside coastal effects.
Item No : 3- Damodar-Mohisila-Kalipahari doubling is a super critical coal project. Plans are there to shift both freight and passenger trains from Burnpur-Asansol line. This new line will establish fast transit between south eastern railway and eastern railway. It will nullify all present detentions.
please wait...Translate to EnglishMy buddy asked about speed limits, speed tests, and track projects from Chandil to Adra.
Info No 1: There's slow down at Anara & Bero due to sharp turns. They're fixing Anara issue in Chandil Burnpur 3rd line. They're also working on a new track alignment at Ramkanali to remove restrictions.
Info No 2: They did a trial at 130 kmph between Chandil and Anara, everything went cool. They're renewing the OHE to reduce resistance and heat.
Info No 3: Doubling project at Damodar-Mohisila-Kalipahari is big. They plan to switch trains from Burnpur-Asansol line for faster transit.