Doubling completed and both up and down lines are open for operations and fully functional between BMO and MED.
.
The down line is the old line from BMO towards MED, the new double line is in the right, alignment takes a shift before the gundla pochampally bridge and the down line is the new line and the up line is the old line. Speed on the new line on both up and down line is 70KMPH. And 30 in the newly inter locked turo outs at BMO, gundla pochampally and MED....
more...
.
Also now the double line is also automatic territory for signalling upto medchal all the wah from SC. HYB division did a great job in finishing the interlocking and signalling in just three days of traffic/engineering block.
.
Also electrification is complete atleast physically, not sure if it is live or not between BMO and MED.