Delhi - Rewari - Jaipur Electrification:
Jul 2018 Status
-----
BWSN Bijwasan - PM Palam
--
Wiring Work between Bijwasan - Shahbad Mohammadpur - Palam 90% FINISHED
No wiring in BWSN Bijwasan Rly Station
No wiring in PM Palam Rly Station
-----
BWSN Bijwasan - PM Palam
--
Elec foundation works finished
Elec Poles are FIXED to foundation 100%
Elec Portals are FIXED to foundation 100%
Crossbeams for Elec Portals FIXED 100%
Elec Poles/ Portals where cantilever assembly FIXED 100%
Wiring completed 90%
-----
PM Palam Rly Stn
--
Elec Poles are FIXED to foundation 100%
Elec Portals are FIXED to foundation 100%
Crossbeams for Elec Portals FIXED 90%
Elec Poles/ Portals where cantilever assembly FIXED 30%
Wiring completed 0% NO WIRING in Station
-----
---------------------